Due Date Company and Proceeding Regulatory Item Order / Letter
2021-11-03 FortisBC Energy Inc. (FEI) and Stargas Utilities Ltd. (Stargas) - Application for Approval of an Asset Disposition and a Certificate of Public Convenience and Necessity (CPCN) to Facilitate the Transfer of Natural Gas Utility Assets from Stargas to FEI

Panel: A. Fung, Chair C. Brewer and W. Everett, Commissioners
Intervener Final Written Argument G-252-21
2021-11-03 FortisBC Energy Inc. - Application for Common Rates and 2022 Revenue Requirements for the Fort Nelson Service Area

Panel: A. Fung, Chair B. Lockhart and A. Pape-Salmon, Commissioners
BCUC Information Request (IR) No. 1 on Common Rates G-277-21
2021-11-03 FortisBC Energy Inc. - Application for Common Rates and 2022 Revenue Requirements for the Fort Nelson Service Area

Panel: A. Fung, Chair B. Lockhart and A. Pape-Salmon, Commissioners
Intervener IR No. 1 on 2022 Delivery Rates G-277-21
2021-11-03 Barriere Ridge Power lnc./Barriere Ridge Resort Ltd. - Application for Partial Relief/Exemption from Public Utility under the Utilities Commission Act, Part 3 and Section 71

Panel: T. Loski, Chair C. Brewer and W. Everett, Commissioners
BR Power to provide proof of delivery to the BCUC G-304-21
2021-11-04 British Columbia Hydro and Power Authority (BC Hydro) – Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)

Panel: D. Morton, Chair A. Fung, R. Mason and A. Pape-Salmon, Commissioners
Intervener IR No. 1 to BC Hydro G-263-21
2021-11-04 British Columbia Hydro and Power Authority - Open Access Transmission Tariff (OATT) Attachment C Amendments Application – Methodology to Assess Available Transfer Capability

Panel: D. Morton, Chair A. Fung and C. Brewer, Commissioners
Intervener IR No. 1 G-294-21
2021-11-04 FortisBC Inc. (FBC) - Annual Review for 2022 Rates

Panel: A. Fung, Chair W. Everett and T. Loski, Commissioners
Intervener Final Argument G-226-21
2021-11-04 FortisBC Inc. (FBC) 2021 Long-Term Electric Resource Plan (LTERP) and Long-Term Demand-Side Management Plan (LT DSM Plan)

Panel: A. Fung, Chair C. Brewer and A. Pape-Salmon, Commissioners
Intervener IRs No. 1 to FBC G-292-21
2021-11-04 Oakridge Energy – Application for a Certificate of Public Convenience and Necessity for a District Energy System

Panel: R. Mason, Chair T. Loski and B. Lockhart, Commissioners
BCUC and Intervener Information Request (IR) No. 2 to Oakridge Energy G-300-21
2021-11-05 British Columbia Hydro and Power Authority (BC Hydro) Application for Mandatory Reliability Standards (MRS) Costs Regulatory Account for Fiscal 2022

Panel: D. Morton (Chair) R. Mason (Commissioner)
BCUC Information Request (IR) No. 1 to BC Hydro G-299-21
2021-11-08 British Columbia Hydro and Power Authority (BC Hydro) – Mandatory Reliability Standards (MRS) Planning Coordinator (PC) Assessment Report

Panel: A. Fung, Chair C. Brewer and W. Everett, Commissioners
BC Hydro reply (if required) R-24-21
2021-11-08 FortisBC Energy Inc. (FEI) - Application for A Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Upgrade Project

Panel: R. Mason, Chair D. Cote and A. Fung, Commissioners
FEI and intervener responses to PIB’s submission on confidentiality of Oral Evidence G-275-21