The BCUC posts upcoming deadlines for proceedings in progress.

The deadlines for items within a proceeding can be found below by searching for the company the BCUC regulates, or by searching the Proceedings page.

Due Date Company and Proceeding Regulatory Item Order / Letter
2022-01-13 FortisBC Energy Inc. - Application for Common Rates and 2022 Revenue Requirements for the Fort Nelson Service Area

Panel: A. Fung, Chair B. Lockhart and A. Pape-Salmon, Commissioners
Procedural Conference on Common Rates** G-277-21
2022-01-18 British Columbia Hydro and Power Authority (BC Hydro) Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN)

Panel: R. Mason, Chair C. Brewer and A. Dennier
BC Hydro responses to BCUC and Intervener IRs No. 2 Exhibit A-6
2022-01-26 FortisBC Energy Inc. (FEI) - Application for A Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Upgrade Project

Panel: R. Mason, Chair D. Cote and A. Fung, Commissioners
FEI Final Argument If no rebuttal evidence G-275-21
2022-01-27 FortisBC Energy Inc. - Application for Common Rates and 2022 Revenue Requirements for the Fort Nelson Service Area

Panel: A. Fung, Chair B. Lockhart and A. Pape-Salmon, Commissioners
FEI Written Reply Argument on 2022 Delivery Rates G-277-21
2022-01-31 British Columbia Utilities Commission (BCUC) Generic Cost of Capital

Panel: D. Morton, Chair A. Fung, K. Keilty, T. Loski, Commissioners
Filing of Evidence by FortisBC Inc. and FortisBC Energy Inc. (collectively FortisBC) G-288-21
2022-02-08 British Columbia Hydro and Power Authority (BC Hydro) – Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)

Panel: D. Morton, Chair A. Fung, R. Mason and A. Pape-Salmon, Commissioners
BCUC IR No. 2 to BC Hydro G-263-21
2022-02-15 British Columbia Hydro and Power Authority (BC Hydro) – Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)

Panel: D. Morton, Chair A. Fung, R. Mason and A. Pape-Salmon, Commissioners
Intervener IR No. 2 to BC Hydro G-263-21
2022-02-16 FortisBC Energy Inc. (FEI) - Application for A Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Upgrade Project

Panel: R. Mason, Chair D. Cote and A. Fung, Commissioners
Intervener Argument - If no rebuttal evidence G-275-21
2022-02-22 British Columbia Utilities Commission (BCUC) Generic Cost of Capital

Panel: D. Morton, Chair A. Fung, K. Keilty, T. Loski, Commissioners
Intervener registration deadline G-288-21
2022-02-25 British Columbia Utilities Commission (BCUC) Generic Cost of Capital

Panel: D. Morton, Chair A. Fung, K. Keilty, T. Loski, Commissioners
Participant Assistance/Cost Award Budget Estimate deadline G-288-21
2022-02-28 British Columbia Utilities Commission (BCUC) Generic Cost of Capital

Panel: D. Morton, Chair A. Fung, K. Keilty, T. Loski, Commissioners
BCUC IR No. 1 on FortisBC’s Evidence G-288-21
2022-03-07 British Columbia Utilities Commission (BCUC) Generic Cost of Capital

Panel: D. Morton, Chair A. Fung, K. Keilty, T. Loski, Commissioners
Intervener and Utilities IR No. 1 on FortisBC’s Evidence G-288-21