The deadlines for items within a proceeding can be found below by searching for the company the BCUC regulates, or by searching the Proceedings page.
Due Date | Company and Proceeding | Regulatory Item | Order / Letter |
---|---|---|---|
2024-04-08 |
BC Utilities Commission Kelowna OWS Utility Inc. Complaint filed by Strata EPS 7397 |
Kelowna OWS submission regarding delay to file the Third Party Engineering Report | Exhibit A-12 |
2024-04-08 |
BC Utilities Commission Kelowna OWS Utility Inc. Complaint filed by Strata EPS 7397 |
Kelowna OWS submission on how it will complete the Third Party Engineering Report | Exhibit A-12 |
2024-04-08 |
BC Utilities Commission Kelowna OWS Utility Inc. Complaint filed by Strata EPS 7397 |
Kelowna OWS to submit Final executed Third-Party Engineer Retainer Agreement with Falcon Engineering | Exhibit A-12 |
2024-04-24 |
Kyuquot Power Resource Assessment Report |
KPL to confirm intent to file rebuttal evidence | Exhibit A-8 |
2024-04-11 |
Creative Energy 2024 Revenue Requirements for the Core Thermal Energy System |
Creative Energy final argument | G-13-24 |
2024-04-23 |
Creative Energy 2024 Revenue Requirements for the Core Thermal Energy System |
Intervener final argument | G-13-24 |
2024-05-06 |
Creative Energy 2024 Revenue Requirements for the Core Thermal Energy System |
Creative Energy reply argument | G-13-24 |
2024-04-09 |
FortisBC Inc. (electric) Electric Vehicle Direct Current Fast Charging Energy-Based Rate |
FBC final argument | G-17-24 |
2024-04-23 |
FortisBC Inc. (electric) Electric Vehicle Direct Current Fast Charging Energy-Based Rate |
Intervener final argument | G-17-24 |
2024-05-07 |
FortisBC Inc. (electric) Electric Vehicle Direct Current Fast Charging Energy-Based Rate |
FBC reply argument | G-17-24 |
2024-05-31 |
BC Hydro Ladore Spillway Seismic Upgrade Project and Strathcona Discharge Upgrade Project - Adjourned |
BC Hydro to provide an update on status of Project cost information for the Projects | G-25-24 |
2024-04-09 |
Other Cambie Gardens Energy Limited Partnership Complaint filed by S.U.C.C.E.S.S. Affordable Housing Society and the City of Vancouver |
Complainants Reply Argument | G-47-24 |
2024-04-09 |
Other Cambie Gardens Energy Limited Partnership Complaint filed by S.U.C.C.E.S.S. Affordable Housing Society and the City of Vancouver |
CGE Reply Argument | G-47-24 |
2024-04-04 |
ICBC 2024 Financial Allocation Methodology |
Intervener IR No. 1 to ICBC | G-51-24 |
2024-04-25 |
ICBC 2024 Financial Allocation Methodology |
ICBC Responses to IRs | G-51-24 |
2024-05-02 |
ICBC 2024 Financial Allocation Methodology |
Letters of Comment Deadline | G-51-24 |
2024-05-09 |
ICBC 2024 Financial Allocation Methodology |
ICBC Reply to Letters of Comment and Final Argument | G-51-24 |
2024-05-16 |
ICBC 2024 Financial Allocation Methodology |
Intervener Final Argument | G-51-24 |
2024-05-23 |
ICBC 2024 Financial Allocation Methodology |
ICBC Reply Argument | G-51-24 |
2024-04-16 |
CB Powerline Rates and Terms of Service |
CBP responses to BCUC IR No. 1 | G-55-24 |
2024-04-30 |
CB Powerline Rates and Terms of Service |
CBP final argument and reply comments, if applicable | G-55-24 |
2024-04-09 |
Creative Energy Rates for the Mount Pleasant District Cooling System |
CEMP responses to BCUC and Intervener IR No. 2 | G-57-24 |
2024-04-18 |
Creative Energy Rates for the Mount Pleasant District Cooling System |
CEMP final argument | G-57-24 |
2024-04-29 |
Creative Energy Rates for the Mount Pleasant District Cooling System |
Intervener final argument | G-57-24 |
2024-05-08 |
Creative Energy Rates for the Mount Pleasant District Cooling System |
CEMP reply argument | G-57-24 |
2024-04-09 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
Deadline to register as an intervener | G-59-24 |
2024-04-09 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
BCUC Information Request (IR) No. 1 to BC Hydro | G-59-24 |
2024-04-16 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
Intervener IR No. 1 to BC Hydro | G-59-24 |
2024-05-16 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
BC Hydro reply to BCUC and intervener IR No. 1; and deadline for filing of letters of comment | G-59-24 |
2024-05-30 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
BC Hydro final argument | G-59-24 |
2024-06-06 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
Intervener final argument | G-59-24 |
2024-06-13 |
BC Hydro Request to Amend Major Capital Projects Filing Guidelines |
BC Hydro reply argument | G-59-24 |
2024-04-04 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities file evidence | G-6-24 |
2024-04-16 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
New utilities and intervener registrations | G-6-24 |
2024-05-02 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
BCUC Information Request (IR) No. 1 on utilities’ evidence | G-6-24 |
2024-05-09 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utility and Intervener IR No. 1 on utilities’ evidence | G-6-24 |
2024-05-30 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities responses to IR No. 1 | G-6-24 |
2024-06-18 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
BCUC notice of remaining regulatory timetable | G-6-24 |
2024-06-25 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Letters of comment deadline - No IR No. 2 | G-6-24 |
2024-07-03 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities final Argument - No IR No. 2 | G-6-24 |
2024-07-09 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
BCUC IR No. 2 on utilities’ evidence - With IR No. 2 | G-6-24 |
2024-07-16 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utility and Intervener IR No. 2 on utilities’ evidence - With IR No. 2 | G-6-24 |
2024-07-17 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Intervener final argument - No IR No. 2 | G-6-24 |
2024-07-31 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities reply argument - No IR No. 2 | G-6-24 |
2024-08-07 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities responses to IR No. 2 - With IR No. 2 | G-6-24 |
2024-08-14 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Letters of comment deadline - With IR No. 2 | G-6-24 |
2024-08-21 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities final argument - With IR No. 2 | G-6-24 |
2024-09-04 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Intervener final argument - With IR No. 2 | G-6-24 |
2024-09-18 |
BC Utilities Commission Generic Cost of Capital Stage 2 |
Utilities reply argument - With IR No. 2 | G-6-24 |
2024-04-19 |
Kyuquot Power Resource Assessment Report |
Response to IRs on intervener evidence | G-60-24 |
2024-05-10 |
Kyuquot Power Resource Assessment Report |
KPL final argument | G-60-24 |
2024-05-24 |
Kyuquot Power Resource Assessment Report |
Intervener final argument | G-60-24 |
2024-06-14 |
Kyuquot Power Resource Assessment Report |
KPL reply argument | G-60-24 |
2024-04-04 |
Nelson Hydro Nelson Hydro 2024 Revenue Requirements |
Nelson Hydro final argument and reply comments, if applicable | G-66-24 |
2024-05-01 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Deadline to request intervener status | G-76-24 |
2024-05-09 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
BCUC Information Request (IR) No. 1 | G-76-24 |
2024-05-16 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Intervener IR No. 1 | G-76-24 |
2024-06-13 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix responses to BCUC and Intervener IR No. 1 | G-76-24 |
2024-06-25 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
BCUC notice of remaining regulatory timetable | G-76-24 |
2024-07-04 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Letters of comment deadline (No IR No. 2) | G-76-24 |
2024-07-09 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
BCUC and Intervener IR No. 2 | G-76-24 |
2024-07-11 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix confirmation of compliance with social media reminder posts (No IR No. 2) | G-76-24 |
2024-07-15 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix final argument and reply to letters of comment (No IR No. 2) | G-76-24 |
2024-07-29 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Intervener final argument (No IR No. 2) | G-76-24 |
2024-07-30 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix responses to BCUC and Intervener IR No. 2 | G-76-24 |
2024-08-08 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Letters of comment deadline (With IR No. 2) | G-76-24 |
2024-08-13 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix reply argument (No IR No. 2) | G-76-24 |
2024-08-15 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix confirmation of compliance with social media reminder posts (With IR No. 2) | G-76-24 |
2024-08-28 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix final argument and reply to letters of comment (With IR No. 2) | G-76-24 |
2024-09-12 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Intervener final argument (With IR No. 2) | G-76-24 |
2024-09-26 |
Corix Burnaby Mountain District Energy Utility 2024-2025 Revenue Requirements and Rates |
Corix reply argument (With IR No. 2) | G-76-24 |
2024-04-26 |
BC Hydro Non-Integrated Areas Planning Regulatory Framework |
BC Hydro responses to BCUC and Intervener IR No. 1 | G-80-24 |
2024-05-16 |
BC Hydro Non-Integrated Areas Planning Regulatory Framework |
Deadline for Letters of comment on the Proposal | G-80-24 |
2024-05-23 |
BC Hydro Non-Integrated Areas Planning Regulatory Framework |
BC Hydro to provide a reply, if any, to the Letters of comment | G-80-24 |
2024-04-04 |
BC Hydro Establishment of the Electric Vehicle Rebate Regulatory Account |
BC Hydro provides confirmation of compliance with Public Notice requirements | G-82-24 |
2024-04-09 |
BC Hydro Establishment of the Electric Vehicle Rebate Regulatory Account |
BCUC Information Request (IR) No. 1 to BC Hydro | G-82-24 |
2024-05-09 |
BC Hydro Establishment of the Electric Vehicle Rebate Regulatory Account |
Letters of comment deadline | G-82-24 |
2024-05-23 |
BC Hydro Establishment of the Electric Vehicle Rebate Regulatory Account |
BC Hydro final argument and reply to letters of comment | G-82-24 |
2024-05-02 |
BC Hydro Establishment of the Electric Vehicle Rebate Regulatory Account |
BC Hydro responses to BCUC IR No. 1 | G-84-24 |
2024-04-18 |
BC Hydro Certificate of Public Convenience and Necessity for Off-Grid Electric Vehicle Charging Stations |
Deadline for letters of comment | G-85-24 |
2024-05-18 |
BC Hydro Certificate of Public Convenience and Necessity for Off-Grid Electric Vehicle Charging Stations |
BC Hydro to provide a reply, if any, to the letters of comment | G-85-24 |
2024-04-02 |
Kyuquot Power Request to Vary 2024 Revenue Requirements Order G-53-24 Directive 4 Scope and Filing Date |
KPL to provide notice of reconsideration application | G-88-24 |
2024-04-04 |
Kyuquot Power Request to Vary 2024 Revenue Requirements Order G-53-24 Directive 4 Scope and Filing Date |
KPL to provide confirmation of compliance with notice of reconsideration application requirements | G-88-24 |
2024-04-09 |
Kyuquot Power Request to Vary 2024 Revenue Requirements Order G-53-24 Directive 4 Scope and Filing Date |
KPL to file supplementary information | G-88-24 |
2024-04-11 |
Kyuquot Power Request to Vary 2024 Revenue Requirements Order G-53-24 Directive 4 Scope and Filing Date |
Letters of comment deadline | G-88-24 |
2024-04-16 |
Kyuquot Power Request to Vary 2024 Revenue Requirements Order G-53-24 Directive 4 Scope and Filing Date |
KPL reply to letters of comment (if any) | G-88-24 |
2024-04-04 |
BC Hydro Open Access Transmission Tariff Attachment M-2 Amendments |
BC Hydro to provide notice of the Application and this order | G-90-24 |
2024-04-09 |
BC Hydro Open Access Transmission Tariff Attachment M-2 Amendments |
BC Hydro to provide written confirmation of notice | G-90-24 |
2024-04-09 |
BC Hydro Open Access Transmission Tariff Attachment M-2 Amendments |
BC Hydro responses to BCUC IR No. 1 | G-90-24 |
2024-04-18 |
BC Hydro Open Access Transmission Tariff Attachment M-2 Amendments |
Letters of comment from interested parties | G-90-24 |
2024-05-02 |
BC Hydro Open Access Transmission Tariff Attachment M-2 Amendments |
BC Hydro response to letters of comment (if applicable) | G-90-24 |
2024-04-11 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
Intervener IR No. 2 to Wyse (if any) | G-92-24 |
2024-04-11 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
BCUC Information Request (IR) No. 2 to Wyse | G-92-24 |
2024-04-25 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
Wyse Response to IR No. 2 | G-92-24 |
2024-05-02 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
Wyse Final Argument | G-92-24 |
2024-05-16 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
Intervener Final Arguments | G-92-24 |
2024-05-28 |
Wyse Meter Solutions Submetering Systems and Rates for Service |
Wyse Reply Argument | G-92-24 |
2024-04-05 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
FBC to publish and provide Notice of the Application | G-97-24 |
2024-04-12 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
FBC to provide confirmation of the Public Notice and a list of all parties notified | G-97-24 |
2024-04-22 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
Intervener registration deadline | G-97-24 |
2024-04-23 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
BCUC information request (IR) No. 1 to FBC | G-97-24 |
2024-05-02 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
Intervener IR No. 1 to FBC | G-97-24 |
2024-05-23 |
FortisBC Inc. (electric) Certificate of Public Convenience and Necessity for the Fruitvale Substation Project |
FBC responses to BCUC and Intervener IRs No. 1 | G-97-24 |
2024-04-02 |
BC Utilities Commission Mandatory Reliability Standards Planning Coordinator function registration and Planning Coordinator Issues |
Planning Coordinator Implementation Proposals | R-56-23 |
2024-05-01 |
BC Utilities Commission Mandatory Reliability Standards Planning Coordinator function registration and Planning Coordinator Issues |
Intervener comment on proposals | R-56-23 |