BC Hydro

Fiscal 2023 to 2025 Revenue Requirements

Completed: 2023

BC Hydro is seeking BCUC approval of a net bill decrease of 1.4% effective April 1, 2022, followed by net bill increases of 2% effective April 1, 2023 and 2.7% effective April 1, 2024, among other items.

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: June 15, 2023 @ 3:25 pm
Decision and G-91-23 Decision and Order April 21, 2023
Decision and G-154-23 Decision and G-154-23 June 19, 2023

Arguments/Submissions

Title Document Description
BC Hydro Final Argument Final Argument October 27, 2022
McCandless Final Argument Final Argument November 22, 2022
BCSEA Final Argument Final Argument November 22, 2022
AMPC Final Argument Final Argument November 24, 2022
AMPC Final Argument Addendum Confidential Final Argument Addendum November 24, 2022
BCOAPO Final Argument Final Argument November 24, 2022
CEC Final Argument Final Argument November 24, 2022
NTC Final Argument Final Argument November 24, 2022
MoveUP Final Argument Final Argument November 24, 2022
FortisBC Final Argument Final Argument November 24, 2022
ZoneIIRPG Final Argument Final Argument November 24, 2022
RCIA Final Argument Final Argument November 24, 2022
BC Hydro Reply Argument Reply Argument December 22, 2022
MoveUP Final Argument on SRP Topics Final Argument on SRP Topics January 23, 2023
AMPC Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
CEC Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
NTC Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
RCIA Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
BCSEA Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
ZoneII-RPG Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
BCOAPO Final Argument on SRP Topics Final Argument on SRP Topics January 24, 2023
MoveUP Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
BCSEA Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
NTC Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
BCOAPO Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
ZoneII-RPG Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
RCIA Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
CEC Argument on AMPC Proposals Argument on AMPC Proposals January 27, 2023
AMPC Reply Argument on SRP Topics Final Argument on SRP Topics February 01, 2023
BCH Reply Argument on SRP Topics Final Argument on SRP Topics February 06, 2023
BC Hydro DARR Submission DARR Submission February 22, 2023
MoveUP DARR Submission DARR Submission February 22, 2023
BCSEA DARR Submission DARR Submission February 23, 2023
BCOAPO DARR Submission DARR Submission February 28, 2023
NTC DARR Submission DARR Submission February 28, 2023
ZoneII-RPG DARR Submission DARR Submission February 28, 2023
CEC DARR Submission DARR Submission February 28, 2023
AMPC DARR Submission DARR Submission February 28, 2023
RCIA DARR Submission DARR Submission February 28, 2023
BC Hydro DARR Reply Submission DARR Reply Submission March 3, 2023
BC Hydro Final Argument Final Argument May 16, 2023
BCSEA Final Argument on Financial Issues Final Argument on Financial Issues May 18, 2023
ZoneII-RPG Final Argument on Financial Issues Final Argument on Financial Issues May 23, 2023
RCIA Final Argument on Financial Issues Final Argument on Financial Issues May 24, 2023
AMPC Final Argument on Financial Issues Final Argument on Financial Issues May 24, 2023
NTC Final Argument on Financial Issues Final Argument on Financial Issues May 24, 2023
BCOAPO Final Argument on Financial Issues Final Argument on Financial Issues May 24, 2023
CEC Final Argument on Financial Issues Final Argument on Financial Issues May 24, 2023
BC Hydro Reply Argument on TIDA Financial Issues Reply Argument on TIDA Financial Issues May 30, 2023

Exhibits

A Exhibits - BCUC Documents

Date Title Document Description
August 20, 2021 A-1 Letter dated August 20, 2021 – Appointing the Panel for the review of British Columbia Hydro and Power Authority Fiscal 2023 to Fiscal 2025 Revenue Requirements Application
September 07, 2021 A-2 Letter dated September 7, 2021 - BCUC Order G-263-21 establishing the regulatory timetable
October 04, 2021 A-3 Letter dated October 4, 2021 – the scope of the BCUC’s review of Demand-Side Management expenditures and Site C costs as part of the current proceeding
October 28, 2021 A-4 Letter dated October 28, 2021 – BCUC Information Request No. 1
October 28, 2021 A-5 CONFIDENTIAL – Letter dated October 28, 2021 – BCUC Confidential Information Request No. 1
December 10, 2021 A-6 Letter dated December 10, 2021 – BCUC approving BC Hydro’s extension request to file Information Request No. 1 responses
December 22, 2021 A-7 Letter dated December 22, 2021 – BCUC response to late request to intervene from E. Gjoshe
December 23, 2021 A-8 Letter dated December 23, 2021 – BCUC response to BC Hydro extension request
February 04, 2022 A-9 Letter dated February 4, 2022 – BCUC Request to BC Hydro regarding access to Confidential Materials
February 08, 2022 A-10 Letter dated February 8, 2022 BCUC Information Request No. 2 to BCH
February 08, 2022 A-11 CONFIDENTIAL – Letter dated February 8, 2022 – BCUC Confidential Information Request No. 2 to BCH
February 09, 2022 A-12 Letter dated February 9, 2022 – BCUC approving extension to file Information Requests on BC Hydro’s supplemental Response to BCOAPO IR 1.87.2
February 22, 2022 A-13 Letter dated February 22, 2022 - BCUC Order G-44-22 regarding AMPC’s request to access Confidential Materials
February 22, 2022 A-14 Letter dated February 22, 2022 – BCUC Order G-47-22 approving interim rates for fiscal 2023
March 11, 2022 A-15 Letter dated March 11, 2022 – BCUC Order G-72-22 amending the regulatory timetable
March 18, 2022 A-16 Letter dated March 18, 2022 – BCUC response to BCH’s submission in compliance with Directives 2 and 3 of Order G-44-22.
April 19, 2022 A-17 Letter dated April 19, 2022 – BCUC submitting procedural conference information
May 18, 2022 A-18 Letter dated May 18, 2022 – BCUC Order G-136-22 establishing a further regulatory timetable with Reasons for Decision
June 16, 2022 A-19 Letter dated June 16, 2022 – BCUC Order G-166-22 amending the regulatory timetable
June 23, 2022 A-20 Letter dated June 23, 2022 – BCUC submitting Information Request No. 3 to BC Hydro
July 08, 2022 A-21 Letter dated July 8, 2022 – BCUC requesting submissions on OIC 355 Direction regarding BCUC Respecting Load Attraction and Low-Carbon Electrification
July 13, 2022 A-22 Letter dated July 13, 2022 – BCUC Order G-189-22 amending the regulatory timetable with Reasons for Decision
July 14, 2022 A-23 Letter dated July 14, 2022 – BCUC Information Request No. 1 to AMPC on Intervener Evidence of Mr. Bowman
July 14, 2022 A-24 Letter dated July 14, 2022 – BCUC Information Request No. 1 to AMPC on Intervener Evidence of Ms. Davies
July 14, 2022 A-25 Letter dated July 14, 2022 – BCUC Information Request No. 1 to RCIA on Intervener Evidence
July 14, 2022 A-26 Letter dated July 14, 2022 – BCUC Information Request No. 1 to Zone II RPG on Intervener Evidence
July 15, 2022 A-27 Letter dated July 15, 2022 – BCUC response to CEC extension request to file Information Request No. 1 on Intervener Evidence
July 29, 2022 A-28 CONFIDENTIAL – Letter dated July 29, 2022 – BCUC response to BCH Submissions on Confidential Documents
August 04, 2022 A-29 Letter dated August 4, 2022 – BCUC response to BC Hydro regarding Confidential Order R 10-22
August 19, 2022 A-30 Letter dated August 19, 2022 – BCUC Order G-239-22 amending the regulatory timetable with Reasons for Decision
August 26, 2022 A-31 Letter dated August 26 2022 – BCUC response to AMPC’s Comments on Order G-239-22
September 01, 2022 A-32 Letter dated September 1, 2022 – BCUC clarification regarding oral hearing topics
September 07, 2022 A-33 Letter dated September 7, 2022 – BCUC Order G-248-22 on oral hearing scope with Reasons for Decision
September 07, 2022 A-34 Letter dated September 7, 2022 – BCUC issuing Oral Hearing Information
September 13, 2022 A-35 Letter dated September 13, 2022 – BCUC clarification regarding September 19 federal holiday
September 16, 2022 A-36 Letter dated September 16, 2022 – BCUC providing further information on oral hearing
October 12, 2022 A-37 Letter dated October 12, 2022 – BCUC Order G-284-22 amending the regulatory timetable
October 18, 2022 A-38 Letter dated October 18, 2022 – BCUC clarification regarding oral hearing transcript amendments
October 28, 2022 A-39 Letter dated October 28, 2022 – BCUC response to AMPC Request for Access to Confidential Information
November 29, 2022 A-40 Letter dated November 29, 2022 – BCUC Order G-344-22 amending the regulatory timetable
December 23, 2022 A-41 Letter dated December 23, 2022 – BCUC Order G-386-22 with amended timetable and Panel IR No. 1
December 23, 2022 A-42 Letter dated December 23, 2022 – BCUC issuing Streamlined Review Process (SRP) Information
January 12, 2023 A-43 Letter dated January 12, 2023 – BCUC submitting Information Request No. 3 on SRP topics to BC Hydro
January 18, 2023 A-44 Letter dated January 18, 2023 – BCUC Order G-10-23 with amended regulatory timetable
January 30, 2023 A-45 Letter dated January 30, 2023 – Commissioner Andrew Pape-Salmon Notice to Parties
February 10, 2023 A-46 Letter dated February 10, 2023 – BCUC requesting submissions regarding the DARR
March 21, 2023 A-47 Letter dated March 21, 2023 – BCUC Order G-60-23 approving interim rates for Fiscal 2024
March 28, 2023 A-48 Letter dated March 28, 2023 – BCUC Order G-66-23 with amended timetable
March 28, 2023 A-49 Letter dated March 28, 2023 – BCUC submitting Panel IR No. 2 to BC Hydro
April 04, 2023 A-50 Letter dated April 4, 2023 – BCUC Order G-74-23 establishing further regulatory timetable
April 20, 2023 A-51 Letter dated April 20, 2023 – BCUC Order G-90-23 establishing further regulatory timetable
April 20, 2023 A-52 Letter dated April 20, 2023 – BCUC submitting Panel IR No. 3 to BC Hydro
May 09, 2023 A-53 Letter dated May 9, 2023 – BCUC Order G-111-23 establishing a further regulatory timetable
June 06, 2023 A-54 Letter dated June 6, 2023 – BCUC requesting submissions regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
June 13, 2023 A-55 Letter dated June 13, 2023 – BCUC amending Panel for the review of the application
October 27, 2021 A2-1 CONFIDENTIAL – Letter dated October 27, 2021 – BCUC staff submitting confidential BC Hydro Compliance Report Pursuant to Directive 8 of the BCUC Decision on the Fiscal 2022 Revenue Requirements Application, September 17, 2021
May 02, 2022 A2-2 Letter dated May 2, 2022 – BCUC staff submitting draft regulatory timetable
July 21, 2022 A2-3 Letter dated July 21, 2022 – BCUC Staff Seek Submission from BC Hydro on Confidential Documents for the Record
July 21, 2022 A2-3-1 Letter dated July 21, 2022 – BCUC Staff submitting Order R-18-19 Notice of Compliance Violation Investigation Pertaining to FAC-003 dated September 9, 2019
July 21, 2022 A2-3-2 Exhibit Withdrawn
July 21, 2022 A2-3-3 Exhibit Withdrawn
July 21, 2022 A2-3-4 CONFIDENTIAL – Letter dated July 21, 2022 – BCUC staff submitting confidential Order R-10-22 dated March 22, 2022
July 29, 2022 A2-4 Letter dated July 29, 2022 – BCUC Staff submitting Order R-28-21 Application for Acceptance of a Mitigation Plan (Version 1) required for Compliance with Mandatory Reliability Standards FAC-003-4 Requirement 2 – Violation ID: BCUC2020000733 FAC-003-4 Requirement 2 – Violation ID: BCUC2020000734 FAC-003-4 Requirement 2 – Violation ID: BCUC2020000735 dated November 4, 2021
July 29, 2022 A2-5 Letter dated July 29, 2022 – BCUC Staff submitting Order R-30-21 Application for Acceptance of a Mitigation Plan (Version 2) required for Compliance with Mandatory Reliability Standard: FAC-003-4 Requirement 4 – Violation ID: BCUC2020000727 dated November 18, 2021
July 29, 2022 A2-6 Letter dated July 29, 2022 – BCUC Staff submitting Order R-26-21 Application for Acceptance of a Mitigation Plan (Version 1) required for Compliance with Mandatory Reliability Standard: FAC-003-3 Requirement 6 – Violation ID: BCUC2020000728 dated November 3, 2021
July 29, 2022 A2-7 Letter dated July 29, 2022 – BCUC Staff submitting Order R-27-21 Application for Acceptance of a Mitigation Plan (Version 1) required for Compliance with Mandatory Reliability Standard: FAC-003-4 Requirement 7 – Violation ID: BCUC2020000729 dated November 3, 2021
July 29, 2022 A2-8 Letter dated July 29, 2022 – BCUC Staff submitting Order R-13-22 Application for Acceptance of a Mitigation Plan (Version 2) required for Compliance with Mandatory Reliability Standard: FAC-003-4 Requirement 2 – Violation ID: BCUC2019000681 dated March 25, 2022
July 29, 2022 A2-9 Letter dated July 29, 2022 – BCUC Staff submitting Fiscal 2022 Revenue Requirements Application Decision and Order G-187-21, pp. 38 and 42 dated June 17, 2021
August 08, 2022 A2-3-4-1 CONFIDENTIAL– Letter dated August 8, 2022 – BCUC staff submitting redacted confidential Order R-10-22 dated March 22, 2022
September 07, 2022 A2-10 Letter dated September 7, 2022 – BCUC Staff submitting Redacted BC Hydro Island Generation EPA Renewal excerpt dated July 29, 2022
September 07, 2022 A2-10-1 CONFIDENTIAL – Letter dated September 7, 2022 – BCUC Staff submitting confidential BC Hydro Island Generation EPA Renewal excerpt dated July 29, 2022
September 23, 2022 A2-11 CONFIDENTIAL – Letter dated September 23, 2022 – BCUC Staff submitting confidential staff calculations

B Exhibits - Applicant Documents

Date Title Document Description
August 13, 2021 B-1 BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Letter dated August 13, 2021 submitting proposed timetable for the review of the Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)
August 31, 2021 B-2 PUBLIC - Letter dated August 31, 2021 – BC Hydro submitting Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)
August 31, 2021 B-2-1 PUBLIC - Letter dated August 31, 2021 – BC Hydro submitting F2023-F2025 RRA Appendix
August 31, 2021 B-2-2 CONFIDENTIAL - Letter dated August 31, 2021 – BC Hydro submitting F2023-F2025 RRA Confidential Chapter 6
August 31, 2021 B-2-3 CONFIDENTIAL - Letter dated August 31, 2021 – BC Hydro submitting F2023-F2025 RRA Confidential Chapter 10 Appendices U, V and W
August 31, 2021 B-2-4 CONFIDENTIAL - Letter dated August 31, 2021 – BC Hydro submitting F2023-F2025 RRA Confidential Appendices I and V
August 31, 2021 B-2-5 CONFIDENTIAL - Letter dated August 31, 2021 – BC Hydro submitting F2023-F2025 RRA Confidential Appendix JJ
September 09, 2021 B-2-1-1 PUBLIC - Letter dated September 9, 2021 – BC Hydro submitting correction to F2023-F2025 RRA Appendix II
September 21, 2021 B-3 Letter dated September 21, 2021 – BC Hydro submitting Submarine Cable Update
September 28, 2021 B-2-3-1 REDACTED - Letter dated September 28, 2021 – BC Hydro submitting F2023-F2025 RRA Redacted Confidential Chapter 10 Appendices U, V and W
October 08, 2021 B-4 Letter dated October 8, 2021 – BC Hydro submitting public notice filing in compliance with G-263-21
October 08, 2021 B-5 Letter dated October 8, 2021 – BC Hydro submitting update on DSM schedule
December 09, 2021 B-6 Letter dated December 9, 2021 – BC Hydro submitting extension request to file Information Request No. 1 responses
December 16, 2021 B-8 Letter dated December 16, 2021 – BC Hydro submitting responses to Interveners Information Request No. 1
December 16, 2021 B-7 Letter dated December 16, 2021 – BC Hydro submitting responses to BCUC Information Request No. 1
December 16, 2021 B-7-1 CONFIDENTIAL - Letter dated December 16, 2021 – BC Hydro submitting confidential responses to BCUC Information Request No. 1
December 16, 2021 B-8-1 CONFIDENTIAL - Letter dated December 16, 2021 – BC Hydro submitting confidential responses to Interveners Information Request No. 1
December 16, 2021 B-9 CONFIDENTIAL - Letter dated December 16, 2021 – BC Hydro submitting confidential responses to BCUC Confidential Information Request No. 1
December 22, 2021 B-10 Letter dated December 22, 2021 – BC Hydro submitting Fiscal 2023 to 2025 Demand-Side Measures expenditure schedule
January 17, 2022 B-7-1-1 CONFIDENTIAL - Letter dated January 17, 2022 – BC Hydro submitting confidential response to BCUC Information Request No. 1.69.5.1
January 17, 2022 B-7-2 PUBLIC - Letter dated January 17, 2022 – BC Hydro submitting public response to BCUC Information Request No. 1.69.5.1
January 19, 2022 B-2-1-2 Letter dated January 19, 2022 – BC Hydro submitting Errata to F2023-F2025 RRA Appendices
January 19, 2022 B-2-2-1 CONFIDENTIAL - Letter dated January 19, 2022 – BC Hydro submitting confidential Errata to F2023-F2025 RRA Confidential Chapter 6
January 19, 2022 B-2-6 Letter dated January 19, 2022 – BC Hydro submitting Errata to F2023-F2025 RRA
January 31, 2022 B-2-1-3 Letter dated January 31, 2022 – BC Hydro submitting Errata to F2023-F2025 RRA Appendix Q
January 31, 2022 B-8-2 Letter dated January 31, 2022 – BC Hydro submitting revised response to RCIA Information Request No. 1.97.1
February 01, 2022 B-11 Letter dated February 1, 2022 – BC Hydro submitting Order G-187-21 Directive 2 compliance
February 04, 2022 B-8-3 Letter dated February 4, 2022 – BC Hydro submitting supplemental response to BCOAPO Information Request No. 1.87.2
February 07, 2022 B-12 Letter dated February 7, 2022 – BC Hydro submitting request for Fiscal 2023 interim rates
February 09, 2022 B-13 CONFIDENTIAL - Letter dated February 9, 2022 – BC Hydro submitting confidential response regarding access to Confidential Materials
February 09, 2022 B-14 CONFIDENTIAL - Letter dated February 9, 2022 – BC Hydro submitting confidential response to AMPC request
March 08, 2022 B-15 Letter dated March 8, 2022 – BC Hydro submitting extension request to file responses to Information Requests No. 2
March 10, 2022 B-16 CONFIDENTIAL – Letter dated March 10, 2022 – BC Hydro submitting G-44-22 compliance regarding market information
March 10, 2022 B-17 Letter dated March 10, 2022 – BC Hydro submission regarding OIC 123 Amendment to Direction No. 8 compliance
March 31, 2022 B-18 CONFIDENTIAL – Letter dated March 31, 2022 – BC Hydro submitting G-44-22 Directive 1 compliance regarding market information
April 14, 2022 B-2-2-2 CONFIDENTIAL - Letter dated April 14, 2022 – BC Hydro submitting confidential Errata No. 4 to F2023-F2025 RRA
April 14, 2022 B-2-7 Letter dated April 14, 2022 – BC Hydro submitting Errata No. 4 to F2023-F2025 RRA
April 14, 2022 B-7-3 Letter dated April 14, 2022 – BC Hydro submitting revised response to BCUC Information Request No. 1 Questions
April 14, 2022 B-8-4 Letter dated April 14, 2022 – BC Hydro submitting revised responses to Intervener Information Request No. 1 Questions
April 14, 2022 B-10-1 Letter dated April 14, 2022 – BC Hydro submitting Errata to Fiscal 2023 to 2025 Demand-Side Measures expenditure schedule
April 14, 2022 B-19 Letter dated April 14, 2022 – BC Hydro submitting responses to BCUC Information Request No. 2
April 14, 2022 B-19-1 CONFIDENTIAL - Letter dated April 14, 2022 – BC Hydro submitting confidential responses to BCUC Information Request No. 2
April 14, 2022 B-20 Letter dated April 14, 2022 – BC Hydro submitting responses to Intervener Information Request No. 2
April 14, 2022 B-20-1 CONFIDENTIAL - Letter dated April 14, 2022 – BC Hydro submitting confidential responses to Intervener Information Request No. 2
April 14, 2022 B-21 CONFIDENTIAL - Letter dated April 14, 2022 – BC Hydro submitting responses to BCUC Confidential Information Request No. 2
April 14, 2022 B-22 CONFIDENTIAL - Letter dated April 14, 2022 – BC Hydro submitting responses to Intervener Confidential Information Request No. 2
April 14, 2022 B-23 Letter dated April 14, 2022 – BC Hydro submitting Transfer Pricing Agreement (Low Carbon Fuel Credits)
May 05, 2022 B-19-2 Letter dated May 5, 2022 – BC Hydro submitting revised response to BCUC Information Requests No. 2
May 05, 2022 B-20-2 Letter dated May 5, 2022 – BC Hydro submitting revised responses to Intervener Information Request No. 2
June 16, 2022 B-24 Letter dated June 16, 2022 – BC Hydro submitting response to RCIA and AMPC extension requests
July 06, 2022 B-25 Letter dated July 6, 2022 – BC Hydro submitting response to Order in Council (OIC) No. 355 Direction
July 08, 2022 B-26 Letter dated July 8, 2022 – BC Hydro submitting extension request to file Intervener Information Request No. 3 responses
July 14, 2022 B-27 Letter dated July 14, 2022 – BC Hydro submitting Information Request No. 1 to AMPC Evidence
July 14, 2022 B-28 Letter dated July 14, 2022 – BC Hydro submitting Information Request No. 1 to RCIA Evidence
July 27, 2022 B-29 CONFIDENTIAL - Letter dated July 27, 2022 – BC Hydro submitting response to BCUC’s request in Exhibit A2-3
July 29, 2022 B-30 Letter dated July 29, 2022 – BC Hydro submitting responses to BCUC Information Requests No. 3
July 29, 2022 B-31 Letter dated July 29, 2022 – BC Hydro submitting responses to Interveners Information Requests No. 3
August 03, 2022 B-32 CONFIDENTIAL - Letter dated August 3, 2022 – BC Hydro submitting response to BCUC’s request in Exhibit A-28
August 08, 2022 B-7-4 Letter dated August 8, 2022 – BC Hydro submitting revised response to BCUC Information Request No. 1 Question 1.13.2
August 08, 2022 B-10-2 Letter dated August 8, 2022 – BC Hydro submitting Errata No. 2 to Fiscal 2023 to 2025 Demand-Side Measures expenditure schedule
August 08, 2022 B-20-3 Letter dated August 8, 2022 – BC Hydro submitting revised responses to ZoneII RPG Information Request No. 2 Question 2.63.3
August 08, 2022 B-30-1 Letter dated August 8, 2022 – BC Hydro submitting revised response to BCUC Information Requests No. 3 Question 3.242.1
August 08, 2022 B-31-1 Letter dated August 8, 2022 – BC Hydro submitting revised responses to AMP Information Request No. 3 Question 3.1.1
August 10, 2022 B-33 Letter dated August 10, 2022 – BC Hydro submission on Oral Hearing Scope
August 12, 2022 B-34 Letter dated August 12, 2022 – BC Hydro reply submission on Oral Hearing Scope
August 23, 2022 B-35 Letter dated August 23, 2022 – BC Hydro submission on Connecting Customers Component of the Electrification Plan
August 29, 2022 B-36 Letter dated August 29, 2022 – BC Hydro submitting rebuttal to evidence from AMPC and RCIA - Depreciation and Net Salvage
August 29, 2022 B-36-1 Letter dated August 29, 2022 – BC Hydro submitting rebuttal to evidence from RCIA - Expected Asset Lives in Asset Management
August 29, 2022 B-36-2 Letter dated August 29, 2022 – BC Hydro submitting rebuttal to evidence from AMPC and RCIA - Vegetation Management
August 29, 2022 B-37 Letter dated August 29, 2022 – BC Hydro reply submission on the Connecting Customers Component of the Electrification Plan
September 01, 2022 B-36-3 Letter dated September 1, 2022 – BC Hydro submitting rebuttal to evidence addendum
September 12, 2022 B-38 Letter dated September 12, 2022 – BC Hydro providing Oral Hearing Opening Statement
September 13, 2022 B-8-5 Letter dated September 13, 2022 – BC Hydro submitting revised responses to Intervener Information Request No. 1
September 13, 2022 B-20-4 Letter dated September 13, 2022 – BC Hydro submitting revised responses to Intervener Information Request No. 2
September 20, 2022 B-39 Submitting at Oral Hearing Sept 20, 2022 - Transcripts from Manitoba Hydro GRA 2012/13 and 2013/14
September 20, 2022 B-40 Submitted at Oral Hearing Sept 20, 2022 - Transcript from Manitoba Hydro GRA 2014/15 and 2015/16
September 20, 2022 B-41 Submitted at Oral Hearing Sept 20, 2022 – Alliance Consulting Group – letter re: Proposed Depreciation Rates Hydro One, April 26, 2021
September 22, 2022 B-42 Submitted by BCH at Oral Hearing September 22, 2022 – BCUC IR and Response from BCH’s Mainwaring Substation Upgrade Project
October 04, 2022 B-43 Letter dated October 4, 2022 – BC Hydro submitting response regarding Oral Hearing Transcript Amendments
October 06, 2022 B-44 Letter dated October 6, 2022 – BC Hydro submitting responses regarding the Undertakings resulting from the Oral Hearing
October 06, 2022 B-44-1 CONFIDENTIAL - Letter dated October 6, 2022 – BC Hydro submitting confidential responses regarding the Undertakings resulting from the Oral Hearing
October 06, 2022 B-45 CONFIDENTIAL - Letter dated October 6, 2022 – BC Hydro submitting confidential responses regarding the In-Camera Undertakings resulting from the Oral Hearing
October 27, 2022 B-46 Letter dated October 27, 2022 – BC Hydro submitting response to Exhibit C7-42
November 09, 2022 B-47 Letter dated November 9, 2022 – BC Hydro submitting confirmation to respond to RCIA Undertaking 13 clarification request
November 09, 2022 B-44-2 Letter dated November 9, 2022 – BC Hydro submitting supplemental response to Undertaking 13
December 15, 2022 B-48 Letter dated December 15, 2022 – BC Hydro submitting Residential and Commercial Customer Account Credits Direction
January 10, 2023 B-49 Letter dated January 10, 2023 – BC Hydro submitting responses to BCUC Panel Information Request No. 1
January 16, 2023 B-49-1 Letter dated January 16, 2023 – BC Hydro submitting revision to response to BCUC Panel Information Request No. 1
January 16, 2023 B-50 Letter dated January 16, 2023 – BC Hydro submitting responses to BCUC Information Request No. 3 on SRP Topics
January 16, 2023 B-51 Letter dated January 16, 2023 – BC Hydro submitting responses to Intervener Information Request No. 3 on SRP Topics
January 19, 2023 B-52 Letter dated January 19, 2023 – BC Hydro submitting Volume 6 Transcript Corrections for SRP on January 16, 2023
February 13, 2023 B-53 Letter dated February 13, 2023 - BC Hydro submitting request for interim F2024 rates
March 09, 2023 B-53-1 Letter dated March 9, 2023 - BC Hydro submitting request for interim F2024 rates - Updated
March 31, 2023 B-54 Letter dated March 31, 2023 - BC Hydro submitting Application to Reinstate a Regulatory Liability to the Trade Income Deferral Account
April 04, 2023 B-55 Letter dated April 4, 2023 – BC Hydro submitting responses to BCUC Panel Information Request No. 2
April 13, 2023 B-56 Letter dated April 13, 2023 – BC Hydro reply submission on Exhibit B-54
May 04, 2023 B-57 Letter dated May 4, 2023 – BC Hydro submitting response to BCUC Panel Information Request No. 3
May 30, 2023 B-58 Letter dated May 30, 2023 – BC Hydro submitting request for clarification of Decision and Order G-91-23 Directives 70 and 71
June 15, 2023 B-59 Letter dated June 15, 2023 – BC Hydro reply submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account

C Exhibits - Intervener Documents

BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated September 9, 2021 Request to Intervene by T. Hackney and W.J. Andrews
MOVEMENT OF UNITED PROFESSIONALS (MOVEUP) – Letter dated September 9, 2021 submitting request to intervene by Jim Quail
FORTISBC ENERGY INC. AND FORTISBC INC. (FORTISBC) – Letter dated September 10, 2021 submitting request to intervene by Diane Roy
CLEAN ENERGY BC (CEBC) – Letter dated September 16, 2021 submitting request to intervene by Laureen Whyte
KWADACHA NATION AND TSAY KEH DENE NATION, TOGETHER THE ZONE II RATEPAYERS GROUP (ZONEII RPG) – Letter dated September 20, 2021 submitting request to intervene by Jana McLean
CAPITAL POWER CORPORATION (CAPITAL POWER) – Letter dated September 20, 2021 submitting request to intervene by Simon Kupi
ASSOCIATION OF MAJOR POWER CUSTOMERS (AMPC) – Letter dated September 24, 2021 submitting request to intervene by Matthew Keen
RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA)– Letter dated September 27, 2021 submitting request to intervene by Fredrik Ambrosson
COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated September 28, 2021 submitting request to intervene by Chris Weafer
NUU-CHAH-NULTH TRIBAL COUNCIL (NTC) – Letter dated September 28, 2021 submitting request to intervene by David Austin
BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SEN IOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY (BCOAPO) – Letter dated September 28, 2021 submitting request to intervene by Leigha Worth, Kristin Barham and Bill Harper
ZONE 1B RATEPAYERS GROUP (Z1BRG) – Letter dated September 29, 2021 submitting request to intervene by Fred J. Weisberg
RICHARD MCCANDLESS (MCCANDLESS) – Letter dated September 21, 2021 submitting request to intervene
CANADIAN MANUFACTURERS AND EXPORTERS (CME) – Letter dated October 05, 2021 submitting late request to intervene by Paul Willis
EDLIRA GJOSHE (GJOSHE) – Letter dated December 19, 2021 submitting late request to intervene


Date Title Document Description
August 27, 2021 C1-2 Letter dated August 27, 2021 – BCSEA submitting Confidentiality Declaration and Undertaking
September 09, 2021 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) - Letter dated September 9, 2021 Request to Intervene by T. Hackney and W.J. Andrews
November 04, 2021 C1-3 Letter dated November 4, 2021 – BCSEA submitting Information Request No. 1 to BC Hydro
February 15, 2022 C1-4 Letter dated February 15, 2022 – BCSEA submitting Information Request No. 2 to BC Hydro
February 22, 2022 C1-4-1 Letter dated February 22, 2022 – BCSEA submitting supplementary Information Request No. 2 to BC Hydro
April 26, 2022 C1-5 Letter dated April 26, 2022 – BCSEA submitting no Intervener Evidence
June 23, 2022 C1-6 Letter dated June 23, 2022 – BCSEA submitting Information Request No. 3 to BC Hydro
July 14, 2022 C1-7 Letter dated July 14, 2022 – BCSEA submitting Information Request No. 1 to ZoneII RPG Evidence
July 14, 2022 C1-8 Letter dated July 14, 2022 – BCSEA submitting Information Request No. 1 to AMPC Evidence
July 14, 2022 C1-9 Letter dated July 14, 2022 – BCSEA submitting Information Request No. 1 to RCIA Evidence
August 11, 2022 C1-10 Letter dated August 11, 2022 – BCSEA submission on Oral Hearing Scope
August 25, 2022 C1-11 Letter dated August 25, 2022 – BCSEA submission on connecting customers component on Electrification Plan
January 11, 2023 C1-12 Letter dated January 11, 2023 – BCSEA submitting Information Request No. 3 to BC Hydro on SRP Topics
April 06, 2023 C1-13 Letter dated April 6, 2023 – BCSEA submission on Exhibit B-54
June 08, 2023 C1-14 Letter dated June 8, 2023 – BCSEA submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
August 30, 2021 C2-2 Letter dated August 30, 2021 – MoveUP submitting Confidentiality Declaration and Undertaking
September 09, 2021 C2-1 MOVEMENT OF UNITED PROFESSIONALS (MOVEUP) – Letter dated September 9, 2021 submitting request to intervene by Jim Quail
November 02, 2021 C2-3 Letter dated November 2, 2021 – MoveUP submitting Information Request No. 1 to BC Hydro
May 06, 2022 C2-4 Letter dated April 26, 2022 – MoveUP submitting Confidentiality Declaration and Undertaking
July 09, 2022 C2-5 Letter dated July 9, 2022 – MoveUP submitting Information Request No. 1 to AMPC Evidence
July 09, 2022 C2-6 Letter dated July 9, 2022 – MoveUP submitting Information Request No. 1 to RCIA Evidence
August 11, 2022 C2-7 Letter dated August 11, 2022 – MoveUP submission on Oral Hearing Scope
September 23, 2022 C2-8 Submitted by MoveUP at Oral Hearing September 23, 2022 –Witness Aid for RCIA Panel on Topic No. 5 Vegetation Management
January 10, 2023 C2-9 Letter dated January 10, 2023 – MoveUP submitting Information Request No. 3 to BC Hydro on SRP Topics
January 11, 2023 C2-9-1 Letter dated January 11, 2023 – MoveUP submitting Supplemental Information Request No. 3 to BC Hydro on SRP Topics
April 10, 2023 C2-10 Letter dated April 10, 2023 – MoveUP submission on Exhibit B-54
September 09, 2021 C3-2 Letter dated September 9, 2021 – FortisBC submitting Confidentiality Declaration and Undertaking
September 10, 2021 C3-1 FORTISBC ENERGY INC. AND FORTISBC INC. (FORTISBC) – Letter dated September 10, 2021 submitting request to intervene by Diane Roy
November 04, 2021 C3-3 Letter dated November 4, 2021 – FortisBC submitting Information Request No. 1 to BC Hydro
February 15, 2022 C3-4 Letter dated February 15, 2022 – FortisBC submitting Information Request No. 2 to BC Hydro
August 11, 2022 C3-5 Letter dated August 11, 2022 – FortisBC submission on Oral Hearing Scope
August 12, 2022 C3-6 Letter submitted August 12, 2022 – FortisBC submitting Confidentiality Declaration and Undertaking
August 31, 2021 C4-2 Letter dated August 31, 2021 – CEBC submitting Confidentiality Declaration and Undertaking
September 16, 2021 C4-1 CLEAN ENERGY BC (CEBC) – Letter dated September 16, 2021 submitting request to intervene by Laureen Whyte
November 04, 2021 C4-3 Letter dated November 4, 2021 – CEBC submitting Information Request No. 1 to BC Hydro
February 15, 2022 C4-4 Letter dated February 15, 2022 – CEBC submitting Information Request No. 2 to BC Hydro
September 03, 2021 C5-3 Letter dated September 3, 2021 – ZoneII-RPG submitting Additional Confidentiality Declaration and Undertaking
September 13, 2021 C5-2 Letter dated September 13, 2021 – ZoneII-RPG submitting Confidentiality Declaration and Undertaking
September 20, 2021 C5-1 KWADACHA NATION AND TSAY KEH DENE NATION, TOGETHER THE ZONE II RATEPAYERS GROUP (ZONEII RPG) – Letter dated September 20, 2021 submitting request to intervene by Jana McLean
November 04, 2021 C5-4 Letter dated November 4, 2021 – ZoneII-RPG submitting Information Request No. 1 to BC Hydro
February 15, 2022 C5-5 Letter dated February 15, 2022 – ZoneII RPG submitting Information Request No. 2 to BC Hydro
April 28, 2022 C5-6 Letter dated April 28, 2022 – ZoneII RPG submitting Notice of Intention to file Intervener Evidence
June 20, 2022 C5-7 Letter dated June 20, 2022 – ZoneII RPG submitting Intervener Evidence
June 23, 2022 C5-8 Letter dated June 23, 2022 – ZoneII RPG submitting Information Request No. 3 to BC Hydro
July 14, 2022 C5-10 Letter dated July 14, 2022 – ZoneII RPG submitting Information Request No. 1 to RCIA Evidence
July 14, 2022 C5-9 Letter dated July 14, 2022 – ZoneII RPG submitting Information Request No. 1 to AMPC Evidence
August 08, 2022 C5-11 Letter dated August 8, 2022 – ZoneII RPG submitting responses to BCUC Information Request No. 1
August 08, 2022 C5-12 Letter dated August 8, 2022 – ZoneII RPG submitting responses to CEC Information Request No. 1
August 08, 2022 C5-13 Letter dated August 8, 2022 – ZoneII RPG submitting responses to BCSEA Information Request No. 1
August 08, 2022 C5-14 Letter dated August 8, 2022 – ZoneII RPG submitting responses to RCIA Information Request No. 1
August 11, 2022 C5-15 Letter dated August 11, 2022 – ZoneII RPG submission on Oral Hearing Scope
August 25, 2022 C5-16 Letter dated August 25, 2022 – ZoneII RPG submission on connecting customers component Electrification Plan
September 23, 2022 C5-17 Letter dated September 23, 2022 – ZoneII RPG submission on further process
November 03, 2022 C5-18 Letter dated November 3, 2022 – ZoneII RPG submission of representative contact information
January 12, 2023 C5-19 Letter dated January 12, 2023 – ZoneII RPG submitting Information Request No. 3 on SRP topics to BC Hydro
April 11, 2023 C5-20 Letter dated April 11, 2023 – ZoneII RPG submission on Exhibit B-54
June 09, 2023 C5-21 Letter dated June 9, 2023 – ZoneII RPG submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
September 20, 2021 C6-1 CAPITAL POWER CORPORATION (CAPITAL POWER) – Letter dated September 20, 2021 submitting request to intervene by Simon Kupi
August 27, 2021 C7-2 Letter dated August 27, 2021 – AMPC submitting Confidentiality Declaration and Undertaking
September 24, 2021 C7-1 ASSOCIATION OF MAJOR POWER CUSTOMERS (AMPC) – Letter dated September 24, 2021 submitting request to intervene by Matthew Keen
November 04, 2021 C7-3 Letter dated November 4, 2021 – AMPC submitting Information Request No. 1 to BC Hydro
December 17, 2021 C7-4 Letter dated December 17, 2021 – AMPC submitting Confidentiality Declaration and Undertaking
February 02, 2022 C7-5 Letter dated February 2, 2022 – AMPC submitting request to access BC Hydro Confidential Information Request responses
February 07, 2022 C7-6 Letter dated February 7, 2022 – AMPC submitting Confidentiality Declaration and Undertaking
February 15, 2022 C7-7 Letter dated February 15, 2022 – AMPC submitting Information Request No. 2 to BC Hydro
February 15, 2022 C7-8 CONFIDENTIAL - Letter dated February 15, 2022 – AMPC submitting confidential Information Request No. 2 to BC Hydro
April 28, 2022 C7-9 Letter dated April 28, 2022 – AMPC submitting Notice of Intention to file Intervener Evidence
June 15, 2022 C7-10 Letter dated June 15, 2022 – AMPC submitting extension request to file Intervener Evidence
June 20, 2022 C7-11 Letter dated June 20, 2022 – AMPC submitting Intervener Evidence of P. Bowman
June 20, 2022 C7-12 Letter dated June 20, 2022 – AMPC submitting Intervener Evidence of M. Davies
June 23, 2022 C7-13 Letter dated June 23, 2022 – AMPC submitting Information Request No. 3 to BC Hydro
July 14, 2022 C7-14 Letter dated July 14, 2022 –AMPC submitting Information Request No. 1 to RCIA Evidence
August 08, 2022 C7-15 Letter dated August 8, 2022 – AMPC submitting responses to BCUC Information Request No. 1 on Bowman Evidence
August 08, 2022 C7-16 Letter dated August 8, 2022 – AMPC submitting responses to CEC Information Request No. 1
August 08, 2022 C7-17 Letter dated August 8, 2022 – AMPC submitting responses to MoveUP Information Request No. 1 on Davies Evidence
August 08, 2022 C7-18 Letter dated August 8, 2022 – AMPC submitting responses to NTC Information Request No. 1
August 08, 2022 C7-19 Letter dated August 8, 2022 – AMPC submitting responses to RCIA Information Request No. 1
August 08, 2022 C7-20 Letter dated August 8, 2022 – AMPC submitting responses to ZoneII-RPG Information Request No. 1
August 08, 2022 C7-21 Letter dated August 8, 2022 – AMPC submitting responses to BC Hydro Information Request No. 1 on AMPC Evidence
August 08, 2022 C7-22 Letter dated August 8, 2022 – AMPC submitting responses to BCOAPO Information Request No. 1
August 08, 2022 C7-23 Letter dated August 8, 2022 – AMPC submitting responses to BCSEA Information Request No. 1 on AMPC Evidence
August 08, 2022 C7-24 Letter dated August 8, 2022 – AMPC submitting responses to BCUC Information Request No. 1 on AMPC Evidence
August 09, 2022 C7-25 Letter dated August 9, 2022 – AMPC submitting Confidentiality Declaration and Undertaking
August 11, 2022 C7-26 Letter dated August 11, 2022 – AMPC submission on Oral Hearing Scope
August 22, 2022 C7-28 Letter dated August 22, 2022 - AMPC submitting comments on BCUC Order G-239-22
August 25, 2022 C7-27 Letter dated August 25, 2022 – AMPC submission on connecting customers component Electrification Plan
September 20, 2022 C7-29 Submitted by AMPC at Oral Hearing September 20, 2022 - Excerpt from AUC Decision on AltaLink 2015-16 GRA, May 9, 2016
September 20, 2022 C7-30 Submitted by AMPC at Oral Hearing September 20, 2022 - Certification for Society of Depreciation Professionals
September 20, 2022 C7-31 Submitted by AMPC at Oral Hearing September 20, 2022 - Excerpt from AUC Decision on AltaLink 2019-20 GRA, NSA, April 16, 2020
September 20, 2022 C7-32 Submitted by AMPC at Oral Hearing September 20, 2022 - Rebuttal Evidence of L. Kennedy submitted in Manitoba Hydro 2015/16 & 2016/17 GRA, May 20, 2015
September 20, 2022 C7-33 Submitted by AMPC at Oral Hearing September 20, 2022 - Excerpt from AUC Decision on AltaLink Stage 2 Review and Variance of Decision 23848-D01-2020 in 2019-2021 GRA, November 19, 2020
September 20, 2022 C7-34 Letter dated September 19, 2022 – AMPC submitting Opening Statement of Patrick Bowman
September 21, 2022 C7-35 Submitted by AMPC at Oral Hearing September 21, 2022 – Excerpts from BCH F12-F14 RRA
September 22, 2022 C7-36 Submitted by AMPC at Oral Hearing September 22, 2022 – Excerpt BCH 2017 Waneta Transaction Application
September 22, 2022 C7-37 Submitted by AMPC at Oral Hearing September 22, 2022 – Opening Statement of Melissa Davies
September 22, 2022 C7-38 Submitted by AMPC at Oral Hearing September 22, 2022 – Excerpt from BCH 2022 RRA
September 22, 2022 C7-39 Submitted by AMPC at Oral Hearing September 22, 2022 – Excerpt from BCH RFP No. 10649
September 22, 2022 C7-40 Submitted by AMPC at Oral Hearing September 22, 2022 – Excerpt from BCH RFP No. 7089
October 07, 2022 C7-41 Letter dated October 7, 2022 – AMPC submitting request for Transcript corrections
October 26, 2022 C7-42 Letter dated October 26, 2022 – AMPC submitting request for access to confidential information
January 12, 2023 C7-43 Letter dated January 12, 2023 – AMPC submitting Information Request No. 3 on SRP topics to BC Hydro
January 13, 2023 C7-44 Letter dated January 13, 2023 – AMPC submitting new evidence at SRP
February 28, 2023 C7-45 Letter submitted February 28, 2023 – AMPC SRP Power Point Presentation
April 11, 2023 C7-46 Letter dated April 11, 2023 – AMPC submission on Exhibit B-54
June 09, 2023 C7-47 Letter dated June 9, 2023 – AMPC submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
September 09, 2021 C8-2 Letter dated September 9th, 2021 – RCIA submitting Confidentiality Declaration and Undertaking
September 27, 2021 C8-1 RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA)– Letter dated September 27, 2021 submitting request to intervene by Fredrik Ambrosson
November 04, 2021 C8-3 Letter dated November 4, 2021 – RCIA submitting Information Request No. 1 to BC Hydro
February 15, 2022 C8-4 Letter dated February 15, 2022 – RCIA submitting Information Request No. 2 to BC Hydro
April 28, 2022 C8-5 Letter dated April 28, 2022 – RCIA submitting Notice of Intention to file Intervener Evidence
June 10, 2022 C8-2-1 Letter dated June 10, 2022 – RCIA submitting revised Confidentiality Declaration and Undertaking
June 14, 2022 C8-2-2 Letter dated June 14, 2022 – RCIA submitting second revised Confidentiality Declaration and Undertaking
June 15, 2022 C8-6 Letter dated June 15, 2022 – RCIA submitting extension request to file Intervener Evidence
June 20, 2022 C8-7 Letter dated June 20, 2022 – RCIA submitting Intervener Evidence on Expected Lives and Depreciation Lives of Selected Assets
June 20, 2022 C8-8 Letter dated June 20, 2022 – RCIA submitting Intervener Evidence on Expected Asset Lives in Asset Management
June 20, 2022 C8-9 Letter dated June 20, 2022 – RCIA submitting Intervener Evidence on Vegetation Management
June 23, 2022 C8-10 Letter dated June 23, 2022 – RCIA will not be submitting Information Request No. 3
July 12, 2022 C8-11 Letter dated July 12, 2022 – RCIA submitting Information Request No. 1 to ZoneII RPG Evidence
July 12, 2022 C8-12 Letter dated July 12, 2022 – RCIA submitting Information Request No. 1 to AMPC Evidence
August 08, 2022 C8-13 Letter dated August 8, 2022 – RCIA submitting responses to BCUC Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-14 Letter dated August 8, 2022 – RCIA submitting responses to BC Hydro Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-15 Letter dated August 8, 2022 – RCIA submitting responses to AMPC Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-16 Letter dated August 8, 2022 – RCIA submitting responses to BCOAPO Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-17 Letter dated August 8, 2022 – RCIA submitting responses to BCSEA Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-18 Letter dated August 8, 2022 – RCIA submitting responses to CEC Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-19 Letter dated August 8, 2022 – RCIA submitting responses to MoveUP Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-20 Letter dated August 8, 2022 – RCIA submitting responses to NTC Information Request No. 1 on RCIA Evidence
August 08, 2022 C8-21 Letter dated August 8, 2022 – RCIA submitting responses to ZoneII-RPG Information Request No. 1 on RCIA Evidence
August 11, 2022 C8-22 Letter dated August 11, 2022 – RCIA submitting Confidentiality Declaration and Undertakings
August 11, 2022 C8-23 Letter dated August 11, 2022 – RCIA submission on Oral Hearing Scope
August 25, 2022 C8-24 Letter dated August 25, 2022 – RCIA submission on connecting customers component Electrification Plan
September 12, 2022 C8-25 Letter dated September 12, 2022 – RCIA submitting Addendums to Exhibits C8-13 and C8 14 respectively, responses to Information Requests No. 1 on RCIA Evidence
September 20, 2022 C8-26 Submitted by RCIA at Oral Hearing September 20, 2022 – Excerpt of slide deck, Society of Depreciation Professionals Annual Conference & Meeting September 2019 by Rick Fisher
September 20, 2022 C8-27 Letter dated September 19, 2022 –RCIA submitting Opening Statements for Oral Hearing
September 22, 2022 C8-28 REVISED - Submitted by RCIA at Oral Hearing September 22, 2022 – Revised Confidentiality Declaration and Undertaking Form
November 01, 2022 C8-29 Letter dated November 1, 2022 – RCIA submitting clarification request regarding Undertaking No. 13
January 11, 2023 C8-30 Letter dated January 11, 2022 – RCIA submitting change of primary contact to M. Matusiak
January 12, 2023 C8-31 Letter dated January 12, 2023 – RCIA submitting Information Request No. 3 on SRP topics to BC Hydro
April 11, 2023 C8-32 Letter dated April 11, 2023 – RCIA submission on Exhibit B-54
June 09, 2023 C8-33 Letter dated June 9, 2023 – RCIA submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
August 31, 2021 C9-2 Letter dated August 31, 2021 – CEC submitting Confidentiality Declaration and Undertaking
September 28, 2021 C9-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated September 28, 2021 submitting request to intervene by Chris Weafer
November 02, 2021 C9-3 Letter dated November 2, 2021 – CEC submitting Confidentiality Declaration and Undertakings
November 04, 2021 C9-4 Letter dated November 4, 2021 – CEC submitting Information Request No. 1 to BC Hydro
February 15, 2022 C9-5 Letter dated February 15, 2022 – CEC submitting Information Request No. 2 to BC Hydro
February 22, 2022 C9-5-1 Letter dated February 22, 2022 – CEC submitting supplementary Information Request No. 2 to BC Hydro
June 23, 2022 C9-6 Letter dated June 23, 2022 – CEC submitting Information Request No. 3 to BC Hydro
July 14, 2022 C9-7 Letter dated July 14, 2022 – CEC submitting extension request to file Information Requests on Intervener Evidence
July 15, 2022 C9-8 Letter dated July 15, 2022 – CEC submitting Information Request No. 1 to ZoneII RPG Evidence
July 15, 2022 C9-9 Letter dated July 14, 2022 – CEC submitting Information Request No. 1 to RCIA Evidence
July 15, 2022 C9-10 Letter dated July 14, 2022 – CEC submitting Information Request No. 1 to AMPC Evidence
August 11, 2022 C9-11 Letter dated August 11, 2022 – CEC submission on Oral Hearing Scope
August 25, 2022 C9-12 Letter dated August 25, 2022 – CEC submission on connecting customers component Electrification Plan
January 12, 2023 C9-13 Letter dated January 12, 2023 – CEC submitting Information Request No. 3 to BC Hydro on SRP Topics
April 11, 2023 C9-14 Letter dated April 11, 2023 – CEC submission on Exhibit B-54
June 09, 2023 C9-15 Letter dated June 9, 2023 – CEC submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
September 28, 2021 C10-1 NUU-CHAH-NULTH TRIBAL COUNCIL (NTC) – Letter dated September 28, 2021 submitting request to intervene by David Austin
November 04, 2021 C10-2 Letter dated November 4, 2021 – NTC submitting Information Request No. 1 to BC Hydro
February 15, 2022 C10-3 Letter dated February 15, 2022 – NTC submitting Information Request No. 2 to BC Hydro
February 22, 2022 C10-3-1 Letter dated February 22, 2022 – NTC submitting supplementary Information Request No. 2 to BC Hydro
June 23, 2022 C10-4 Letter dated June 23, 2022 – NTC submitting Information Request No. 3 to BC Hydro
July 14, 2022 C10-5 Letter dated July 14, 2022 – NTC submitting Information Request No. 1 to AMPC Evidence
July 14, 2022 C10-6 Letter dated July 14, 2022 – NTC submitting Information Request No. 1 to RCIA Evidence
August 11, 2022 C10-7 Letter dated August 11, 2022 – NTC submission on Oral Hearing Scope
September 21, 2022 C10-8 Submitted by NTC at Oral Hearing September 21, 2022 – Roadmap
September 21, 2022 C10-9 Submitted by NTC at Oral Hearing September 21, 2022 – Truth and Reconciliation Commission of Canada – Calls to Action
September 21, 2022 C10-10 Submitted by NTC at Oral Hearing September 21, 2022 – Declaration on the Rights of Indigenous Peoples Act, [SBC 2019] Chapter 44
September 21, 2022 C10-11 Submitted by NTC at Oral Hearing September 21, 2022 - BC Hydro Mandate letter Aug 17, 2017
September 21, 2022 C10-12 Submitted by NTC at Oral Hearing September 21, 2022 - BC Hydro Statement of Indigenous Principles
September 21, 2022 C10-13 Submitted by NTC at Oral Hearing September 21, 2022 – BCH Financial Information Act Return for the Year Ended March 31, 2021
September 21, 2022 C10-14 Submitted by NTC at Oral Hearing September 21, 2022 – Extract from BC Hydro Site C Quarterly Progress Report No. 25 to the BCUC
September 21, 2022 C10-15 Submitted by NTC at Oral Hearing September 21, 2022 – Extract from BC Hydro Site C Quarterly Progress Report No. 1 to the BCUC
January 12, 2023 C10-16 Letter dated January 12, 2023 – NTC submitting Information Request No. 3 to BC Hydro on SRP Topics
April 11, 2023 C10-17 Letter dated April 11, 2023 – NTC submission on Exhibit B-54
September 28, 2021 C11-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SEN IOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY (BCOAPO) – Letter dated September 28, 2021 submitting request to intervene by Leigha Worth, Kristin Barham and Bill Harper
November 04, 2021 C11-2 Letter dated November 4, 2021 – BCOAPO submitting Information Request No. 1 to BC Hydro
November 05, 2021 C11-3 Letter dated November 5, 2021 – BCOAPO submitting Confidentiality Declaration and Undertakings
February 15, 2022 C11-4 Letter dated February 15, 2022 – BCOAPO submitting Information Request No. 2 to BC Hydro
February 22, 2022 C11-4-1 Letter dated February 22, 2022 – BCOAPO submitting supplementary Information Request No. 2 to BC Hydro
June 23, 2022 C11-5 Letter dated June 23, 2022 – BCOAPO submitting Information Request No. 3 to BC Hydro
July 14, 2022 C11-7 Letter dated July 14, 2022 – BCOAPO submitting Information Request No. 1 to RCIA Evidence
July 14, 2022 C11-6 Letter dated July 14, 2022 – BCOAPO submitting Information Request No. 1 to AMPC Evidence
August 12, 2022 C11-8 Letter dated August 11, 2022 – BCOAPO submission on Oral Hearing Scope
August 25, 2022 C11-9 Letter dated August 25, 2022 – BCOAPO submission on connecting customers component on Electrification Plan
September 22, 2022 C11-10 Submitted by BCOAPO at Oral Hearing September 22, 2022 – IR and Response from BCH’s Application Peace to Kelly Lake
January 12, 2023 C11-11 Letter dated January 12, 2023 – BCOAPO submitting Information Request No. 3 on SRP topics to BC Hydro
April 11, 2023 C11-12 Letter dated April 11, 2023 – BCOAPO submission on Exhibit B-54
June 09, 2023 C11-13 Letter dated June 9, 2023 – BCOAPO submission regarding the Fiscal 2022 Depreciation Study Impact Regulatory Account
September 29, 2021 C12-1 ZONE 1B RATEPAYERS GROUP (Z1BRG) – Letter dated September 29, 2021 submitting request to intervene by Fred J. Weisberg
September 21, 2021 C13-1 RICHARD MCCANDLESS (MCCANDLESS) – Letter dated September 21, 2021 submitting request to intervene
November 03, 2021 C13-2 Letter dated November 3, 2021 – McCandless submitting Information Request No. 1 to BC Hydro
February 14, 2022 C13-3 Letter dated February 14, 2022 – McCandless submitting Information Request No. 2 to BC Hydro
April 07, 2023 C13-4 Letter dated April 7, 2023 – McCandless submission on Exhibit B-54
October 05, 2021 C14-1 CANADIAN MANUFACTURERS AND EXPORTERS (CME) – Letter dated October 05, 2021 submitting late request to intervene by Paul Willis
November 04, 2021 C14-2 Letter dated November 4, 2021 – CME submitting Information Request No. 1 to BC Hydro
February 14, 2022 C14-3 Letter dated February 14, 2022 – CME submitting Information Request No. 2 to BC Hydro
December 19, 2021 C15-1 EDLIRA GJOSHE (GJOSHE) – Letter dated December 19, 2021 submitting late request to intervene
February 15, 2022 C15-2 Letter dated February 15, 2022 – Gjoshe submitting Information Request No. 2 to BC Hydro
September 11, 2022 C15-3 Letter dated September 11, 2022 – Gjoshe submitting status change requesting withdrawal from Intervener Status

D Exhibits — Interested Party Documents

Date Title Document Description
September 22, 2021 D-1 BROWNLOW, H. (BROWNLOW) – Submission dated September 22, 2021 Request for Interested Party Status
November 03, 2021 D-2 UNIVERSITY OF BRITISH COLUMBIA (UBC) - Submission dated November 3, 2021 Request for Interested Party Status by Joshua Wauthy
December 28, 2022 D-3 BRUDY, S. (BRUDY) – Submission dated December 28, 2022 Request for Interested Party Status
January 13, 2023 D-4 CANADIAN ASSOCIATION OF PETROLEUM PRODUCERS (CAPP) - Submission dated January 13, 2023 Request for Interested Party Status by Geoff Morrison
March 31, 2023 D-5 BRYENTON, R. (BRYENTON) – Submission dated March 31, 2023 Request for Interested Party Status

E Exhibits - Letters of Comment

Date Title Document Description
April 11, 2023 E-4 MINISTER OF ENERGY, MINES AND LOW CARBON INNOVATION (EMLI) – Letter of Comment dated April 11, 2023
January 27, 2022 E-3 TAYLOR, D. (TAYLOR) – Letter of Comment dated January 27, 2022
September 22, 2021 E-2 BARROW, W. (BARROW) – Letter of Comment dated September 22, 2021
September 17, 2021 E-1 GARTSHORE, I. (GARTSHORE) – Letter of Comment dated September 17, 2021

Transcripts

Date Title Document Description
May 06, 2022 Transcript Volume 1 Procedural Conference May 6, 2022
September 20, 2022 Transcript Volume 2 PM Oral Hearing September 20, 2022
September 20, 2022 Transcript Volume 2 AM Oral Hearing September 20, 2022
September 21, 2022 Transcript Volume 3 PM Oral Hearing September 21, 2022
September 21, 2022 Transcript Volume 3 PM - Special Errata Oral Hearing September 21, 2022
September 21, 2022 Transcript Volume 3 AM Oral Hearing September 21, 2022
September 22, 2022 Transcript Volume 4 PM Oral Hearing September 22, 2022
September 22, 2022 Transcript Volume 4 AM Oral Hearing September 22, 2022
September 22, 2022 Transcript Volume Confidential In-Camera September 22, 2022
September 23, 2022 Transcript Volume 5 AM Oral Hearing September 23, 2022
October 18, 2022 Transcript Volumes 2 to 5 Erratas Erratas received October 18, 2022
January 16, 2023 Transcript Volume 6 Streamlined Review Process January 16, 2023
January 16, 2023 Transcript Volume 6 Errata Streamlined Review Process January 16, 2023 Errata

Our Review Process

Learn more about how we review applications, which are submitted to us by the entities we regulate. You'll see the types of reviews we conduct and how you can get involved in the process.

Learn more