British Columbia Hydro and Power Authority (BC Hydro) Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN)

In Progress

To get involved in this proceeding, please click the button below.

Get Involved

Timetable

Subject Date
BC Hydro responses to BCUC and Intervener IRs No. 1 Tuesday, November 9, 2021
BCUC and Intervener IR No. 2 to BC Hydro Tuesday, December 14, 2021
BC Hydro responses to BCUC and Intervener IRs No. 2 Tuesday, January 18, 2022

Hearing and Other Documents

Title Document Description
EXHIBIT LIST Updated: October 25, 2021 @ 2:58 pm

Exhibits

A Exhibits — BCUC Documents

Date Title Document Description
August 23, 2021 A-1 Letter dated August 23, 2021 – BCUC Panel Appointment for the review of the BC Hydro Bridge River Projects – Certificates of Public Convenience and Necessity Application
August 26, 2021 A-2 Letter dated August 26, 2021 – BCUC Order G-253-21 establishing a regulatory timetable
October 05, 2021 A-3 Letter dated October 5, 2021 – BCUC Information Request No. 1 to BC Hydro
October 05, 2021 A-4 CONFIDENTIAL Letter dated October 5, 2021 – BCUC Confidential Information Request No. 1 to BC Hydro
October 08, 2021 A-5 Letter dated October 8, 2021 – BCUC Order G-291-21 amending the regulatory timetable
October 13, 2021 A-6 Letter dated October 13, 2021 – BCUC notice to parties regarding the amended regulatory timetable

B Exhibits — Applicant Documents

Date Title Document Description
July 23, 2021 B-1 PUBLIC - BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN) dated July 23, 2021
July 23, 2021 B-1-1 Letter dated July 23, 2021 – BC Hydro submitting public Appendix A to the application
July 23, 2021 B-1-2 Letter dated July 23, 2021 – BC Hydro submitting public Appendix B-BR1 to the application
July 23, 2021 B-1-3 Letter dated July 23, 2021 – BC Hydro submitting public Appendix C-BRT to the application
July 23, 2021 B-2 CONFIDENTIAL - BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (BC HYDRO) – Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN) Application dated July 23, 2021
July 23, 2021 B-2-1 CONFIDENTIAL - Letter dated July 23, 2021 – BC Hydro submitting confidential Appendix A to the application
July 23, 2021 B-2-2 CONFIDENTIAL - Letter dated July 23, 2021 – BC Hydro submitting confidential Appendix B BR1 to the application
July 23, 2021 B-2-3 CONFIDENTIAL - Letter dated July 23, 2021 – BC Hydro submitting confidential Appendix C BRT to the application
September 22, 2021 B-3 Letter dated September 22, 2021 – BC Hydro submitting compliance with Order G-253-21 Directives 2, 3 and 4

C Exhibits — Intervener Documents

Date Title Document Description
August 24, 2021 C1-1 BC SUSTAINABLE ENERGY ASSOCIATION (BCSEA) – Letter dated August 24, 2021 submitting request to intervene by William Andrews
October 19, 2021 C1-2 Letter dated October 19, 2021 - BCSEA submitting Information Request No. 1 to BC Hydro
September 28, 2021 C2-1 BRITISH COLUMBIA OLD AGE PENSIONERS’ ORGANIZATION, ACTIVE SUPPORT AGAINST POVERTY, DISABILITY ALLIANCE BC, COUNCIL OF SENIOR CITIZENS’ ORGANIZATIONS OF BC, TENANTS RESOURCE AND ADVISORY CENTRE, AND TOGETHER AGAINST POVERTY SOCIETY (BCOAPO) – Letter dated September 28, 2021 submitting request to intervene by Kristin Barham
October 19, 2021 C2-2 Letter dated October 19, 2021 - BCOAPO submitting Information Request No. 1 to BC Hydro
September 28, 2021 C3-1 RESIDENTIAL CONSUMER INTERVENER ASSOCIATION (RCIA) – Letter dated September 28, 2021 submitting request to intervene by Fredrik Ambrosson
October 19, 2021 C3-2 Letter dated October 19, 2021 - RCIA submitting Information Request No. 1 to BC Hydro
October 25, 2021 C3-3 Letter dated October 25, 2021 - RCIA submitting Confidentiality Declaration and Undertakings
September 28, 2021 C4-1 COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BRITISH COLUMBIA (CEC) – Letter dated September 28, 2021 submitting request to intervene by Chris Weafer
October 08, 2021 C4-2 Letter dated October 8, 2021, CEC submitting extension request to file Information Requests No. 1
October 19, 2021 C4-3 Letter dated October 19, 2021 - CEC submitting Information Request No. 1 to BC Hydro
October 18, 2021 C4-4 Letter dated October 18, 2021 - CEC submitting Confidentiality Declaration and Undertakings
September 28, 2021 C5-1 BC SOLAR AND STORAGE INDUSTRIES ASSOCIATION (BCSSIA) – Letter dated September 28, 2021 submitting request to intervene by Steve Davis
October 19, 2021 C5-2 Letter dated October 19, 2021 - BCSSIA submitting Information Request No. 1 to BC Hydro