Due Date Company and Proceeding Regulatory Item Order / Letter
2021-11-08 British Columbia Hydro and Power Authority (BC Hydro) – Mandatory Reliability Standards (MRS) Planning Coordinator (PC) Assessment Report

Panel: A. Fung, Chair C. Brewer and W. Everett, Commissioners
BC Hydro reply (if required) R-24-21
2021-11-12 British Columbia Hydro and Power Authority (BC Hydro) Application for Mandatory Reliability Standards (MRS) Costs Regulatory Account for Fiscal 2022

Panel: D. Morton (Chair) R. Mason (Commissioner)
BC Hydro response to BCUC IR No. 1 G-299-21
2021-11-15 British Columbia Hydro and Power Authority - Open Access Transmission Tariff (OATT) Attachment C Amendments Application – Methodology to Assess Available Transfer Capability

Panel: D. Morton, Chair A. Fung and C. Brewer, Commissioners
BC Hydro Responses to BCUC and Intervener IR No. 1 G-294-21
2021-11-09 British Columbia Hydro and Power Authority (BC Hydro) Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN)

Panel: R. Mason, Chair C. Brewer and A. Dennier
BC Hydro responses to BCUC and Intervener IRs No. 1 Exhibit A-6
2021-12-13 British Columbia Hydro and Power Authority (BC Hydro) – Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)

Panel: D. Morton, Chair A. Fung, R. Mason and A. Pape-Salmon, Commissioners
BC Hydro responses to BCUC and Intervener IRs No. 1 G-263-21
2022-01-18 British Columbia Hydro and Power Authority (BC Hydro) Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN)

Panel: R. Mason, Chair C. Brewer and A. Dennier
BC Hydro responses to BCUC and Intervener IRs No. 2 Exhibit A-6
2022-03-31 British Columbia Hydro and Power Authority (BC Hydro) – Fiscal 2023 to Fiscal 2025 Revenue Requirements Application (F2023-F2025 RRA)

Panel: D. Morton, Chair A. Fung, R. Mason and A. Pape-Salmon, Commissioners
BC Hydro responses to BCUC and Intervener IRs No. 2 G-263-21
2021-11-26 British Columbia Hydro and Power Authority (BC Hydro) Application for Mandatory Reliability Standards (MRS) Costs Regulatory Account for Fiscal 2022

Panel: D. Morton (Chair) R. Mason (Commissioner)
BC Hydro responses to letters of comment G-299-21
2021-10-28 British Columbia Hydro and Power Authority (BC Hydro) Public Electric Vehicle (EV) Fast Charging Rate Application

Panel: D. Morton , Chair A. Fung and B. Lockhart, Commissioners
BC Hydro written reply argument Exhibit A-27
2021-11-04 Oakridge Energy – Application for a Certificate of Public Convenience and Necessity for a District Energy System

Panel: R. Mason, Chair T. Loski and B. Lockhart, Commissioners
BCUC and Intervener Information Request (IR) No. 2 to Oakridge Energy G-300-21
2021-12-14 British Columbia Hydro and Power Authority (BC Hydro) Bridge River Projects – Certificates of Public Convenience and Necessity (CPCN)

Panel: R. Mason, Chair C. Brewer and A. Dennier
BCUC and Intervener IR No. 2 to BC Hydro Exhibit A-6
2021-11-19 FortisBC Energy Inc. (FEI) - Application for A Certificate of Public Convenience and Necessity (CPCN) for the Okanagan Capacity Upgrade Project

Panel: R. Mason, Chair D. Cote and A. Fung, Commissioners
BCUC confirmation of cross-examination of PIB’s experts G-275-21